single phase transformer 50hz 200 kva 11kv/230v test results: no load test: input=1600watts short circuit test : 2600watts calculate all day efficiency duty cycle 160kw 0.8 pf 8 hr 100kw unity pf 6hr remaining hrs no load Answer

almost 11 years ago