can you explain the problem

over 11 years ago
Swati pulk...
Tiny_avatar26

Answers

0
total work =x work done by A in one day= x/12 B is 60% more efficient,so work done by B= (1.6*x)/12 total time taken by B= x/{ (1.6*x)/12}=7.5